Origin Issues Notice to Proceed on 300 MW grid-forming battery at Mortlake

Australian Renewable Energy Agency (ARENA) 2 mins read

Mortlake in Victoria’s west is set to be bolstered with further grid supporting services through a new 300 MW / 650 MWh battery developed by Origin Energy (Origin), with Origin issuing Notice to Proceed to the EPC Contractor, Fluence, last week.

Initially announced in late 2022 on behalf of the Australian Government, the Australian Renewable Energy Agency (ARENA) will provide up to $24 million in funding to the project, as part of the $176 million Large Scale Battery Storage Funding Round (Funding Round).

At a total cost of around $400 million, the battery, situated near the existing Mortlake Power Station, will provide grid forming and stability services to the region's growing number of wind and solar farms, particularly in Victoria’s South West Renewable Energy Zone. Fluence has been appointed as the EPC contractor and will utilise grid forming inverters supplied by SMA. 

The Funding Round allocated funding to eight grid scale battery projects across Australia. Each battery will be equipped with grid-forming inverter technology, allowing them to provide essential system stability services.

ARENA has been instrumental in some of Australia’s earliest large scale batteries, having previously provided $81 million to 8 battery projects prior to the Funding Round, including the 150 MW / 300 MWh Riverina Battery at Darlington Point and the 150 MW / 194 MWh Hornsdale Power Reserve in South Australia, which are currently the largest operation grid-forming batteries in Australia.

ARENA CEO Darren Miller said the project highlights the growing importance of grid forming capabilities for the energy grid.

“As traditional forms of energy generation are phased out, new clean technologies are required to take their place. Large scale batteries can play a significant role in providing system stability services, particularly when fitted with advanced grid forming inverters.”

“ARENA’s funding has been integral to creating smarter batteries with this technology. This is the fifth project to have been committed under the Funding Round, with three more to go across Australia.”

“The decision to proceed by Origin further highlights the increased confidence in grid-forming inverter technology and the strong market incentives driving investment in battery storage.”

The battery is expected to be commissioned in late 2026.

Five of the eight projects that were successful in the Funding Round have been financially committed. These include: 

Neoen
Project: Western Downs BESS
Size (MW / MWh): 255 / 510
Inverter OEM: Tesla

Neoen
Project: Blyth BESS
Size (MW / MWh): 200 / 400
Inverter OEM: Power Electronics

Neoen
Project: VBB BESS (retrofit of grid-forming capability)
Size (MW / MWh): 300 / 450
Inverter OEM: Tesla

AGL
Project: Liddell BESS
Size (MW / MWh): 500 / 1,000
Inverter OEM: Power Electronics

Origin
Project: Mortlake BESS
Size (MW / MWh): 300 / 650
Inverter OEM: SMA

Media

More from this category

  • Energy, Political
  • 06/12/2024
  • 08:30
Climate Media Centre

Talent alert: Hunter locals speak out on nuclear risks as political inquiry comes to town

Friday, December 6 A political hearing in Muswellbrook next week will hear from Hunter Valley locals on their opposition to building nuclear reactors in the region. The federal Parliament’s select committee on nuclear energy is looking into a scheme from the Coalition to build nuclear reactors at sites around the country, including in the Hunter. Local doctors, former coal workers, workers’ advocates and others advocating for the Hunter’s renewable power future are speaking out against the scheme. They say the community wants investment in safe and reliable renewable power, not risky nuclear reactors in the region. They are concerned about…

  • Energy, Environment
  • 05/12/2024
  • 15:32
Climate Council

The seven ways the Federal Coalition could cook the books on nuclear costings

FOR IMMEDIATE RELEASE5 DECEMBER 2024 AUSTRALIANS ARE BEING KEPT IN THE DARKabout the true costs of the Federal Coalition’s risky and expensive nuclear scheme. The Federal Coalition's heavy reliance on the first of two Frontier Economics reports paints a damning picture of the methods they may use to fudge the nuclear numbers and mislead Australians. We've already seen them cherry-pick numbers and use them to make misleading claims in Parliament. Climate Councillor and economistNicki Hutley said: “The Federal Coalition's nuclear scheme would cost Australians a bomb. It’s a risky, expensive fantasy that would see Australians paying more than $100 billion…

  • Energy, Indigenous
  • 05/12/2024
  • 09:00
Pilbara Solar

First Nations co-owned grid-scale solar project shovel ready

Pilbara Solar, a 50% Aboriginal-controlled startup business and recognised social enterprise, has received an Offer to Connect for the Junja Solar Farm to deliver power to Horizon Power’s coastal network. “This is the final milestone in developing our first renewable energy project, a 10MW solar farm on our community land at Jinparinya near Port Hedland,” said Barry Taylor, spokesperson for the Jinparinya Community. “Income earned from he project will be put back into the community for social and housing programs,” Mr Taylor said. “The benefits of this project include 5% free carry ownership; the chance to increase our ownership with…

Media Outreach made fast, easy, simple.

Feature your press release on Medianet's News Hub every time you distribute with Medianet. Pay per release or save with a subscription.