- The Queensland Productivity Commission's interim report into Australia's 2025 environmental legislation reforms has been welcomed by Cement Concrete & Aggregates Australia (CCAA), which says the recommendations could reduce regulatory duplication, improve investment certainty and maintain strong environmental protections.
- Prior to the 2025 reforms, environmental approvals for Queensland projects took more than 1,150 days on average, costing project proponents an estimated $4.9 billion to $7.7 billion annually in delays.
- Queensland's cement, concrete and aggregates industry contributes $3.35 billion annually to the state's economy and supports nearly 15,000 jobs, making efficient approval processes critical as the state faces growing demand for construction materials driven by housing targets, a $119 billion infrastructure pipeline and the Brisbane 2032 Olympic and Paralympic Games.
- CCAA has advocated for a genuine bilateral approval framework based on an assess once, approve once principle, and welcomes the Commission's recommendations to explore greater alignment between Queensland and Commonwealth environmental offset requirements to reduce duplication.
- In response to CCAA's concerns about bioregional planning, the Commission recommended a staged, risk-based approach to designating development and conservation zones, with CCAA emphasising that such plans must account for future construction material demand and protect access to strategically important resources.
Cement Concrete & Aggregates Australia (CCAA) has welcomed the release of the Queensland Productivity Commission’s interim report into the Australian Government’s 2025 environmental legislation reforms, saying its recommendations provide an important opportunity to reduce regulatory duplication, improve investment certainty and maintain strong environmental protections.
The Commission found that, prior to the 2025 reforms to the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act), environmental approvals of Queensland projects were taking more than 1,150 days on average, with associated delays estimated to cost Queensland project proponents between $4.9 billion and $7.7 billion annually.
Efficient and predictable environmental approval processes are particularly important for Queensland’s cement, concrete and aggregates industry, which underpins the State’s construction supply chain, contributes $3.35 billion annually to the economy and supports 14,858 jobs.
CCAA Chief Executive Officer Michael Kilgariff said the Commission’s findings reinforced the importance of timely environmental approvals as Queensland faces growing demand for heavy construction materials.
“Queensland has ambitious housing targets, a record $119 billion infrastructure pipeline and the Brisbane 2032 Olympic and Paralympic Games to deliver,” Mr Kilgariff said.
“With demand for hard rock quarry materials in South East Queensland forecast to exceed existing production capacity, efficient and predictable EPBC approvals are increasingly important for brownfield quarry expansions and new greenfield quarries, as well as for sand and gravel extraction, cement plant upgrades and concrete batching facilities where those projects trigger Commonwealth assessment.
“Delivering Queensland’s housing and infrastructure commitments requires reliable and local supplies of heavy construction materials, with regulatory settings that enable industry to invest and expand production in line with demand.”
The Commission’s interim report examines several priorities raised in CCAA’s July submission, including Commonwealth–State bilateral agreements for environmental assessment and approvals, closer alignment of Queensland and Commonwealth environmental offset requirements, bioregional planning and how the EPBC Act’s continuous use exemptions apply to existing operations.
“CCAA has consistently advocated for a genuine bilateral approval framework based on the principle of ‘assess once, approve once’,” Mr Kilgariff said.
“Removing unnecessary duplication between Commonwealth and State approval processes can improve productivity and investment certainty without compromising environmental standards.”
CCAA welcomes the Commission’s recognition of industry concerns regarding continuous use exemptions and supports the Commission’s recommendations to explore greater recognition of Queensland environmental offsets under Commonwealth requirements, reducing duplication where both regimes apply to the same project.
In response to concerns raised by CCAA regarding bioregional planning, the Commission has recommended a staged, risk-based approach to the designation of development and conservation zones.
“Quarries can only operate where suitable geological resources exist, and proximity to markets is critical to keeping construction costs down,” Mr Kilgariff said.
“Bioregional plans must consider future demand for construction materials, protect access to strategically important resources and allow site-specific evidence to inform approval decisions.
“Strong environmental protection and improved productivity are not mutually exclusive. The success of these reforms will ultimately depend on how effectively they are implemented.
“Queensland has an opportunity to establish a more efficient, predictable and proportionate environmental approvals framework that supports investment in the materials needed to deliver the State’s housing and infrastructure commitments.”
CCAA looks forward to participating in the Commission’s upcoming stakeholder roundtables and providing a further submission on the interim report.
About us:
About CCAA
CCAA is the voice of Australia’s heavy construction materials industry, an industry that contributes $20.7 billion to GDP and supports 112,970 jobs nationwide. CCAA members produce most of Australia's cement, concrete and aggregates, which are essential to the nation’s building and construction sectors.
Contact details:
Contact: Mitch Itter, Manager Communications | 0431 542 660 | [email protected]